Contract Variation - Oxford Street West and Liverpool Street Cycleway

Decision Maker: Council

Decision status: Recommendations Determined

Decision:

It is resolved that:

(A)      Council approve additional contract contingency for the construction contract with Mack Civil Pty Ltd for the construction of the Oxford Street West and Liverpool Street Cycleway works, as outlined in Confidential Attachment A to the subject report;

(B)      Council approve the additional funds sought for the Oxford and Liverpool Street Cycleway project as detailed in Confidential Attachment A to the subject report; and

(C)      authority be delegated to the Chief Executive Officer to negotiate and enter into any documentation required to give effect to these resolutions.

Carried unanimously.

X039654

Report author: Mir Hossain

Publication date: 23/06/2025

Date of decision: 23/06/2025

Decided at meeting: 23/06/2025 - Council

Accompanying Documents: