Item for Information - Transport Proposals Approved Through Direct Staff Delegation - July 2026

16/07/2026 - Item for Information - Transport Proposals Approved Through Direct Staff Delegation - July 2026

2026/366016

Recommendations

It is recommended that the Forum note the following traffic and transport proposals approved under Delegation 72b) of the Register of Delegations from CEO to directors and staff (18 December 2025) and in accordance with the TfNSW 2025 Authorisation and Delegation Instrument.

Item

TRIM reference

Location

Proposal Type

Approval Date

1

2026/282443

Barwon Park Road, St Peters

EV Parking

15 June 2026

2

2026/281300

20-28 Munni Street, Newtown

Works Zone

5 June 2026

3

2026/279928

34-36 Dalmeny Avenue, Rosebery

Timed Parking

5 June 2026

4

2026/273185

Dangar Place, Chippendale (122-126 Cleveland Street, Chippendale)

Works Zone

5 June 2026

5

2026/317499

Buckland Street, Alexandria

EV Parking

16 June 2026

6

2026/281254

Forbes Street, Darlinghurst

EV Parking

30 June 2026

7

2026/268518

Liverpool Street, Darlinghurst

EV Parking

22 June 2026

8

2026/268259

Kent Street, Millers Point

EV Parking

22 June 2026

9

2026/317320

Ivy Street, Darlington

Mobility parking

5 June 2026

10

2024/345623

William Street, Redfern

No Parking

5 June 2026

11

2026/356690

O'Loughlin Street, Surry Hills

Works Zone

23 June 2026

12

2026/356043

Defries Avenue, Zetland

Works Zone

24 June 2026

13

2026/315894

Dangar Place

Works Zone

5 June 2026

 

Forum Members for this Item

 

City of Sydney

Transport for NSW

NSW Police – NSW Police – All PACs

Representatives for the Members for Sydney, Heffron, Newtown and Balmain

 

Consultation & Financial Impacts

Item

Proposal Type

Consultation

Financial Impacts

1

EV Parking

Barwon Park Road forms part of the boundary between the City of Sydney and Inner West Council. The eastern side of the road falls within the City of Sydney, while the western side is within Inner West Council.

The parking changes apply only to the eastern side, which is within the City’s Local Government Area. Residents in the surrounding area were not notified as there are no residential properties within 50 metres of the affected section. This area is largely adjacent to Sydney Park.

 

Funds are available in the current Traffic Operations New Signs and Lines budget.

2, 4, 11-13

Works Zone

Applicants must notify adjacent properties at least 14 days prior to the implementation of the Works Zone

All costs associated with implementing the proposal will be borne by the Applicant.

3

Timed Parking

The Development Applicant must notify adjacent properties at least seven days prior to the implementation of the changes.

All costs associated with implementing the proposal will be borne by the Applicant.

Item

Proposal Type

Consultation

Financial Impacts

5

EV Parking

No submissions received

Funds are available in the current Traffic Operations New Signs and Lines budget.

6

EV Parking

2 submissions received supporting and 3 submissions received opposing the proposal due to loss of on-street parking.

The loss of one on-street permit parking space as a result of the proposal was relocated to Liverpool Street along a redundant No Parking space. As such, there's no net loss of on-street parking.

Funds are available in the current Traffic Operations New Signs and Lines budget.

7

EV Parking

3 submissions received supporting and 1 submission received opposing the proposal.

Funds are available in the current Traffic Operations New Signs and Lines budget.

8

EV Parking

4 submissions received supporting and 1 submission received opposing the proposal.

Funds are available in the current Traffic Operations New Signs and Lines budget.

9

Mobility parking

No submissions received either supporting or opposing the proposal.

One submission received that provided feedback on the proposal.

Funds are available in the current Traffic Operations New Signs and Lines budget.

10

No Parking

No submissions received either supporting or opposing the proposal

Funds are available in the current Traffic Operations New Signs and Lines budget.

 

 

CITY OF SYDNEY TRAFFIC OPERATIONS TEAM